Dec 2025
•
Procurement Planning
Finalize supplier selection, issue POs for major components (PV panels, inverters, batteries, etc.).
Nov 2025
•
Detailed Engineering & Design
Final system sizing, electrical drawings, single-line diagrams, BOM preparation.
Sep 2025
•
Stakeholder Approvals & Permits
Secure permits, land rights, grid connection approvals. Begin ESG assessments.
Aug 2025
•
Project Initiation & Feasibility Study
Site visit, load assessment, financial analysis, and preliminary design.